Equinox Gold Q2 2023 Earnings Call Transcript

There are 9 speakers on the call.

Operator

Thank you for standing by. This is the conference operator. Welcome to Equinox Gold's Second Quarter 2023 Results and Corporate Update. As a reminder, all participants are in listen only mode and the conference is being recorded. After the presentation, there will be an opportunity to ask conference call.

Operator

If you're participating through the webcast, You can submit a question in writing by using the text box in the lower left corner of the webcast frame. I would now like to turn the I'll turn the conference over to Verlyn Bailey, Vice President, Investor Relations for Equinox Gold. Please go ahead.

Speaker 1

Thank you, Gayleen, and thank you everybody for joining us this morning. We will of course be making a number of forward looking statements today, so please do visit our continuous disclosure documents our website on SEDAR and in EDGAR. I'd now like to turn the call over to our CEO and President, Greg Smith.

Speaker 2

Thanks, Herlyn, and good morning and thanks everyone for Joining us today, especially at this very early hour on the West Coast here. On the call with me is our CEO, Doug Reddy our CFO, Peter Hardy Our EVP of Exploration, Scott Heffernan and our VP of Investor Relations, Rylin Bailey, who you just heard from. As a quick introduction to those new to the company, Equinox is a diversified, America's focused gold producer. We have 7 producing mines across Brazil, Mexico and the United States. And we also have several growth projects, including our large scale Greenstone gold mine in Ontario, which is in construction now with our 40% joint venture partner Orion Mine Finance.

Speaker 2

So today, we're discussing our 2023 second quarter financial and operating results. But before we jump into those results, I just want to It's the fatality at our Santa Luz mine in June. This was a tragic incident and we extend our deepest sympathies to our employees, family, friends and coworkers. We had a 1 week site wide suspension of operations at Santa Luz to facilitate the investigation and to refresh safety training. I'll now start with a broad overview for the quarter, and then I'll turn over the call to Pete and Doug for more details.

Speaker 2

We had a solid quarter with sales of just over 138,000 ounces at a cash cost per ounce sold of $13.61 and an all in sustaining cost per ounce sold of $15.02 For the 1st 6 months of the year, we sold 261,000 ounces Cash cost of $13.54 per ounce and all in sustaining cost of $15.76 per ounce. This reflects record sales for the company for the 1st 6 months of the year We remain on track to meet our 2023 production and cost guidance. On Tuesday this week, we issued a press release with a full Greenstone update. For those that didn't see it, the team at Greenstone has done a great job of continuing to advance the mine on time and on budget for first gold pour in the first half of twenty twenty four. As of July 21, we were 85% complete overall at Greenstone.

Speaker 2

There's loads of pictures on the website and you can really see how far the projects come and advance over the course of this year. And Doug will have more to say on Greenstone in a few minutes. During the quarter, we also continued to progress the feasibility study on the addition of an underground mine at Aurizona, and we're going to continue to conduct work including trade off studies on throughput from the underground mine. This means we'll complete the study next year. This timing also allows us Potential for a long life underground mine in Aurizona.

Speaker 2

So we're keeping our foot on the gas in terms of development while we progress feasibility study and Doug will also comment more on this. We finished the quarter with unrestricted cash balance of 174,000,000 Approximately $130,000,000 available from our credit facility for a total of over $300,000,000 in available cash liquidity at quarter end. With cash flow from operations, this leaves us well funded through the completion of construction at Greenstone. We also published our 3rd comprehensive ESG report in May. And just recently in July, we published our first water stewardship report.

Speaker 2

These reports summarize our performance during 2022, our targets for 2023 and our long term strategy across a range of ESG initiatives. They're both available on our website along with our Climate Action Report and I encourage everyone on this call to check them out. So with that, I'd like to hand the call over to Peter Hardy to run through our financial results.

Speaker 3

Thanks, Greg. We're now on Slide 6 in the presentation. From a gold sales and revenue perspective, we had our best first half of a year in the company's history. During the quarter, For the 138,000 ounces we sold, we received an average realized price of $19.62 per ounce, that's $19.31 year to date, Generating $272,000,000 in revenue, dollars 506,000,000 year to date, we sold 15,000 more ounces in Q2 as compared to Q1 of this year and about 18,000 more ounces than we did for the 120,000 ounces that we sold in Q2 last year. Our cash cost per ounce of $13.61 for Q2 is similar to that of Q1 of this year and down from Q2 Q2 last year of $14.82 Our all in sustaining cost per ounce of Q2 this year of $15.02 is down from Q1's $16.76 and also down from Q2 last year, last year's $16.57 As to forward views on input costs, unit prices, We're now starting to see decreases, particularly diesel and cyanide in Brazil and the U.

Speaker 3

S. Those unit cost decreases in Brazil are somewhat offset by of the real against the U. S. Dollar. Our EBITDA in Q2 2023 was $64,000,000 or $71,000,000 on an adjusted basis, and we had net income of 5 For basic and fully diluted earnings per share of $0.02 On an adjusted basis, we had a net loss of $6,000,000 or $0.02 a share.

Speaker 3

Cash flow from operations before changes in working capital was $81,000,000 or $0.26 a share. Included in that cash flow from operations as a receipt of an additional $10,000,000 from the gold prepaid arrangement. If you back out those funds, we generated $71,000,000 in cash flow from operations or about $0.22 a share. In terms of liquidity and capital position, we ended the quarter with $174,000,000 of Cash and $127,000,000 available to draw on our credit facility, giving us total liquidity of a little over 300,000,000 We did draw the remainder of the revolver on August 1. Further to the gold sale prepaid transactions entered Q1, as I mentioned, we did enter into an additional gold sale prepay on June 23, whereby With one of our one of the members of the syndicate that provided the prepay, we received $10,000,000 in exchange for delivering to the lender 2 60 3 ounces of gold per month from October 24 to July 26 for a total of just under 6,000 ounces.

Speaker 3

Those terms reflect and that delivery period reflects that of the prepay that we did earlier in the year. Concurrent with the execution of the gold prepay sale transaction in June, we entered in this financial swap Agreements that fix the gold price relating to that $10,000,000 at $2,109 per ounce. Net debt increased from $113,000,000 at the end of Q1 to $548,000,000 pardon me, going from $548,000,000 to $661,000,000 at the end of Q2. On Slide 7, what does that mean for Greenstone? Based on progress to date, we believe our share of the remaining construction budget is about $170,000,000 and we expect to fund that our cash that we had at the end of the quarter, our operating cash flow and the final draw on the revolving credit facility.

Speaker 3

Additionally, we still have the $100,000,000 accordion feature in place. And with those sources of liquidity, as Greg mentioned, we believe we're well funded to complete Greenstone construction. With that, I will turn the time over for Doug to review the operations.

Speaker 4

Thanks, Pete. So as mentioned earlier, we had a very good first half of the year and we are looking at pushing hard to deliver Strong production in the second half. We've noted before that about 55% of production this year is in the second half of the year. At Mesquite, the Brownie pit provided majority of new ore, about 90% of the ore going to leach pad And re leaching on portions of the pad also contributed significantly to the Q2 gold production. Mining costs at Mesquite benefited From a drop in diesel prices and just for example, the current price is about 30% lower than it was in Q2 last year.

Speaker 4

Process costs were reduced through reduction of cyanide and lime usage. We don't see that staying Same in the second half because we plan on stacking more in the second half, so the overall cost will go up on cyanide and lime. At Castle Mountain, throughput has increased 40% since the start of the year in the crusher, and the crusher run time is up by about 30%. We continue with modifications to the crusher setup and we're planning for those additional modifications to be implemented in Q3. At Los Filos, productivity improvements were seen in both open pit and underground.

Speaker 4

Open pit has about 15% higher productivity along with Loading improvements and an increase in effective operating hours for underground is about 23% increase in the ore tons being mined. So although we but although we have more tonnes going to the leach pad, we did have some challenges on the leach pad that we've been addressing. These include some higher copper ore coming from the Guadalupe open pit. I do note that this is only a portion of the ore and it represents about 12% And pipes in one area of the pad, those have since been repaired and the product the pregnant solution in that area where the breakage occurred needs to be drained. That impacts about 8,000 ounces.

Speaker 4

That is slow in coming out of the pad. It will come out. It's just going to be slower and get coming out than originally anticipated. And we also had one portion of the leach pad, which had to be turned again and leached again After a carbonate precipitation occurred, which has hindered recovery, that impacts about 4,000 ounces. Again, those ounces will come out in the second half of the year.

Speaker 4

At Aurizona, in addition to the The current mining contractor, we also mobilized a second contractor with articulated dump trucks. They'll be in for most of the rest of 2023. They came in during the rainy season. The rainy season is over now. We're putting a big push on the mining and to establish a larger stockpile In advance of the next rainy season.

Speaker 4

At Fazenda, we're currently mining mostly from open pits, while the underground also Catches up on development and we'll work on bringing additional stopes into production. Drilling continues on the reserve replacement program Matt Fazenda, it's been successful every year and we continue doing that to successful in replacing reserves every year. At RDM, we had good performance from the owner operated fleet. That fleet is a combination of our own trucks plus 15 60 ton rental trucks. The increase in mining of higher grade in situ ore has brought the production up significantly in the quarter.

Speaker 4

And the mill feed is I'll note that mill feed is also being augmented with low grade stockpiles if there is any availability in the mill. At Santa Luz, the team continues to gradually bring recovery up, and the plant had an average overall recovery of 67% in the quarter. We are targeting 70% or better for the remainder of the year, and the team continues to work on process and throughput improvements. So moving on to Greenstone. I get the pleasure of being able to speak about a really good Story on construction progress, the team has done a great job.

Speaker 4

We put out the Greenstone update news release on Tuesday And provided a complete summary of the project status. Essentially, the project is on budget and on schedule for H1 twenty twenty four production. Moving on to the next page, looking at progress. Overall progress at Greenstone is 85% complete, Which is comprised of construction at 83% complete, engineering is 100% complete and procurement 87% complete. Capital spend at June 30 is $937,000,000 which is 76% complete of the budget on 100% basis, and we have approximately $170,000,000 remaining as Equinox Gold's Share to fund through to project completion.

Speaker 4

Facilities handed over to operations so far are The permanent effluent water treatment plant, truck shop, warehouse, sewage treatment plant, potable water treatment plant, The pit and plant site fuel stations, reagent storage building and site mixed emulsion or explosives plant. The Ministry of Transport Patrol Yard has been turned over to the Ministry and the dismantling of the old patrol yard is now complete. Highway 11 realignment is also complete and has now been transferred to the ministry and was open to the public a few days ago. And the natural gas pipeline to site has been commissioned and is now operational. Plant site is 70 5% complete.

Speaker 4

The TSF is 80% complete. Operations are now at 240 employees. We'll get to around 360 We look forward to hosting an analyst and investor visit in early September. And now moving on to our other expansion projects. At Castle Mountain, we continue in permitting.

Speaker 4

We've responded to queries BLM and we anticipate permitting being complete in 2025. In the meantime, we continue with engineering work and with met test work to support The Phase 2 of Castle Mountain. At Aurizona, as Greg mentioned, we've been advancing the engineering studies These incorporate additional drilling and the recent work looked at the underground mining at a higher production rate given the large scale of the underground resource. And we see benefits in continuing to advance our studies on operating with both open pit and underground to concurrently fill the plant. So we are looking we are planning on developing an exploration decline in H1 2024, Which would provide us an opportunity to develop down to 1 of the ore zones, mine in the ore zone and enable collection of geotechnical and hydrogeological information on ore and wall rock.

Speaker 4

The plan is to have a fully dimension decline that would serve as a production access and would also enable a rapid start to underground production when we've completed our additional studies. And then at Filos, we continue to assess the opportunity to invest in CIL, but we do remain opportunities for capital investment on other projects. So with that, I'm going to hand it back to Greg.

Speaker 2

Thanks, Doug. I think I'll just make a final comment here to thank the entire Equinox Gold team In Vancouver and at all of our sites as well as our shareholders and other stakeholders for their continued support and Finish up there and pass it back to Rylin for Q and A.

Speaker 1

Perfect. Thanks. Ghislaine, can you please remind people how to ask a question?

Operator

If you're participating through the webcast, you can submit a question in writing by using the text box in the lower left corner of the webcast frame. We will pause for a moment as callers join the queue.

Speaker 1

Thank you. Well, there's no online questions yet. So you can go ahead and take questions from the phone, please.

Operator

Thanks. The first question is from Kerry Smith with Haywood Securities. Please go ahead.

Speaker 5

Thanks, operator. Good morning, everybody, and congratulations on a good quarter. I had a couple of questions, Greg. First one was on Greenstone, there was $177,000,000 of contingency built in to that $1,230,000,000 CapEx. How much of that have you actually spent so far on the project?

Speaker 5

Has it been roughly proportionate to the percentage spend that you've completed on the project? Or has it been more or less?

Speaker 2

No, it's roughly proportionate, Carrie. And when we talk about amounts left to spend, we're assuming that we go through that contingency. So it's included in the initial total budget amount. We think we're going to come in at that total budget amount.

Speaker 5

Okay. Okay. That's Helpful. Thanks. And then the second question I had, just on the convertible notes, the $140,000,000 that are due next April, what is the plan or the strategy to deal with those notes to try and roll them out?

Speaker 2

Yes, it's something we've been kind of working on I think that there's a couple of options. Obviously, our first choice would be that they're well in the money and we issue that equity, but You can't always plan for that. So we are talking to the holders, Mubadala, who are very constructive. And of course, we have other options available to us In terms of the market. So, it is something that's on our radar, Carey, and at some point, we'll report what we're doing on that specifically.

Speaker 5

Okay. But do you think you'd have a strategy in place by Q3 or is that something that's going to fall into early next year?

Speaker 2

Whenever you've got debt maturing within a year and especially when you're in a large capital program like this, I think it makes sense to be Ahead of it rather than too tied up against it. So if we can have something done over the course of the next several months, I think that would be our preference.

Speaker 5

Yes, I would agree. Okay. And then the last question I had, how much CapEx do you think there will be left to fund for Greenstone in 2024?

Speaker 3

Hey, Carey, it's Pete. We believe $170,000,000 will get us through to the point where we don't need to fund CapEx anymore. So The budget that we prepared assumes it's all of the CapEx that the partners are going to have to provide the project before it's able to take care of itself And support itself.

Speaker 5

And how much of that $170,000,000 will flow into the next fiscal year though roughly?

Speaker 3

We're on track for the $277,000,000 we were going to spend this year. And sorry, I don't have that split between this year and Sure, at my fingertips.

Speaker 5

Okay. Maybe Raline can

Operator

The next question is from Anita Soni with CIBC. Please go ahead.

Speaker 6

Hi. I'll just follow-up on that. And I believe it's $180,000,000 that you spent to date or into June 30 of the $277,000,000 So I assume that's about $70,000,000 left for next year. Is that correct?

Speaker 3

Yes, Anita. Thanks for clarifying.

Speaker 6

Thanks. Okay. So I have a couple of questions. Just firstly on the leach inventory. I think there was some buildup in Q1 and then some additional buildup in Q2.

Speaker 6

Can you just give me an idea of how much is allocated to each one of the assets? I believe the majority is to Los Filos, right?

Speaker 3

Yes, that's fair.

Speaker 6

Yes. Okay. Are there any others? I noticed like Santa Luz and Mesquite, I had to put some inventory adjustments to get into the cash costs in the ASIC that you were reporting?

Speaker 4

There is some Mesquite And a smaller amount at Castle, but it's predominantly Los Filos.

Speaker 5

Was there anything else I can say? We do maintain,

Speaker 2

We do maintain, Anita, a fairly large stockpile at Santa Luz. That's how we manage the blend of the ore going into the mill. And so the mining has exceeded throughput at Santa Luz and we are working at building and maintaining a fairly large stockpile there. It's just more complicated than the other mines because you're trying to manage around the total organic carbon in the ore. And that Next time you go there, you'll see.

Speaker 2

It's a stockpile inventory management before anything goes into the mill.

Speaker 6

Okay. So that's broken or above ground stocks rather than something in the

Speaker 2

Yes. Yes.

Speaker 6

Okay. And then my second

Speaker 3

I guess the final comment, Anita, on Santa Luz is they also built up their spare parts consumables inventory balances a little over the first half of this year as well. You might see that in the inventory figure, that sounds.

Speaker 6

Okay. So for the remaining assets, I think it was Los Filos, Mesquite that we were talking about in Castle Mountain, those should probably reverse over the course of the year. I think you said for sure at Los Filos, but I just want to confirm for Mesquite.

Speaker 4

Yes, for Filos and Mesquite, yes.

Speaker 6

Okay. And then just on sorry, just on Greenstone. I think we are as I mentioned $180,000,000 a year to date on the spend. So how do we how is it going to play out for Q3 and Q4? Like is it really bulky in Q3 your spend and then tapers down into Q4 for the $277,000,000 that you had said?

Speaker 6

I think, as I mentioned, there was about $100,000,000 left for this year in the back half of the year?

Speaker 3

Yes, that's right, Anita. We do expect that kind of typical S curve. There's a lot of activity happening now, And then you'll see tapering through Q4.

Speaker 6

Okay. And then I think I had one more question and that was I've forgotten. I'll get back into the queue. Thanks.

Speaker 1

We've got a question from an investor in Kuala Lumpur Asking just can you give any more clarity on how things are going at Felipe and when you might be able to start the expansion there?

Speaker 4

Like I said earlier, at the moment, we're monitoring the status in Mexico in general, but also in the region. We continue with the current heap leach operations, mining from Los Filos Open Pit, Los Filos Underground, Bermejal Open Pit and Guadalupe Open Pit. And we are Advancing in our discussions with the communities as well, but we haven't picked the timing yet. It's Rushing into it with Filos when we have other development projects also on the go at Aurizona and Castle Mountain, We are judicious on how we deploy our capital.

Speaker 2

Yes. No decision will come on Filos during 2023. Maybe in 2024, we can provide more clarity.

Speaker 1

Operator, do you want to take Anita's follow-up call?

Operator

Certainly, the next question is from Anita Soni with CIBC.

Speaker 6

Hi, I'm back. So it was a question with regards to the Capital. So I think you spent about 35% year to date. And I just want to get an idea, You did mention that you'll be spending it over the back half of the year, the remaining $65,000,000 But will it be all $65,000,000 Or do you expect to come in a little bit under what you had previously guided to?

Speaker 3

Yes. We are planning on Catching up on that sustaining spend, Anita. We deferred some equipment expenditure at Belo's RDM, we deferred some of the tailings work into the second half of the year. We had planned on doing some of that work in Q2. So yes, we do plan on doing that in the second The year.

Speaker 3

We believe we're on track for our full spend for the year.

Speaker 6

Okay. And is it an even split between Q3 and Q4?

Speaker 4

It's always heavily weighted into Q4.

Speaker 3

Yes. It's that somewhat, call it, typical operations pattern where Yes, you head into budgeting and my managers, our general managers recognize that they got behind on the Sustaining spend, I want to get it done before the end of the year. So you can just, yes, assume that we'll have more in Q4.

Speaker 6

Okay. You got to move up their budget deadlines to like to the 31st or something. Get them going. Okay. Thanks.

Speaker 6

And so higher sustaining capital spend in Q4, but lower sustaining capital spend Sorry, lower development capital spend at Greenstone in Q4?

Speaker 2

Correct.

Speaker 6

Okay. Thank you.

Operator

The next question is from Wayne Lam with RBC. Please go ahead.

Speaker 7

Okay, great. Thanks guys. Just wondering at Santa Luz, obviously, Very unfortunate situation this past quarter. Can you just provide a bit more detail into what happened in terms of breaching safety protocols?

Speaker 2

No, Wayne. The answer is no. And the reason is because we haven't really Out of respect for the employees, family, colleagues, we're not going into any details publicly on what happened.

Speaker 7

Okay, got it. Thanks. And then maybe At Greenstone, really nice to see things on track. Just wondering with the project 85% complete, $170,000,000 left to spend and $300,000,000 in cash with the revolver fully drawn. Are you guys Seeing any additional large spend or bottleneck that aims ahead as you enter the home stretch here?

Speaker 3

The short answer, Wayne, is no. The focus is on we're in that phase Towards the tail end of construction, it's a fairly linear relationship between the amount of piping and electrical installation you have And the manpower that you have doing it and their productivity rate, they've made great progress through the summer, which is What was planned and very fortunately, they're staying on schedule on that front. So it's really just Keeping working that schedule, maintaining the productivity rates that we need. We're happy with our commissioning readiness. And we had a great report from Greenstone yesterday that the recruiting is going very well in relation to operational readiness.

Speaker 3

We had an external review of our operational readiness by another group, which also went well. So with respect to what we have left, based on all the feedback that we have from our work internally, From the assessments that we have done by independent groups, we don't believe right now that we do have bottlenecks that have significant remaining risk, unmitigated risk related to them.

Speaker 2

And Doug referenced Employee how many employees we have today and where we need to get to by the end of the year. We're in a pretty heavy recruitment drive to ramp up the workforce. That's actually going really well. It was a little challenging like a few months ago. We had our own questions of whether we'd get there, but As the mines advanced, we've been able to really increase the level of workforce for operations quite quickly and It looks like we're on track for year end.

Speaker 2

But that was one area where we definitely knew we had to focus. But now we just got a full update And things are going very well at Greenstone and hopefully you're coming Wayne in September and you can see it for yourself.

Speaker 7

Yes, yes, that definitely plan to be there. And it sounds like you guys are in a pretty comfortable spot. Just wanted to confirm, the original CapEx number had about $125,000,000 in fleet purchases. Can you remind me if you guys had moved to fleet financing and you happen to have an estimate of what kind of operating cost impact that might have as we kind of look out to next year?

Speaker 3

We did move to fleet financing, Wayne, and we haven't done any guidance on what 2020 Foreign and operations look like. So we don't have an update on how that might affect operating costs. We will obviously provide that As part of our 2024 guidance when we release it, but it's not something that we have today.

Speaker 7

Okay, got it. And then maybe just last one for me. Just on the inflationary impacts, do you guys have any percentage estimate on How much consumables have kind of eased versus your budget? And then some of your peers have noted Quite a bit of offset on the input cost easing, just given the stronger local currencies in Mexico and Brazil. And just wondering If you guys are feeling those pressures as well as an offset to the input costs And have you been managing that?

Speaker 3

Yes. So prior to consideration That FX strength that you see in Brazil and Mexico, we are starting to see some tapering and unit input costs, which we're obviously very happy to see. In Mexico, even prior to consideration of FX, With respect to diesel, PEMEX, the government, I should say, or PEMEX, they tend to buffer Fuel price increases, but at the same time, when fuel prices taper, there's an effect where Buffered as well. So while we have seen fuel come off, as Doug already mentioned, quite reasonably In the U. S.

Speaker 3

And also in Brazil, we haven't seen that necessarily in Mexico. With respect to FX, yes, the FX in Brazil and Mexico is almost effectively offsetting the unit price decreases that we're seeing. With respect and then with regards to cost management, we hedge about 50% of the near term FX That we have in Mexico and Brazil, that's been helping some, which is why you see realized gains on our FX in our financials. That's what that program is. Hopefully, that gives you a rough idea of what we're seeing and how we try and manage the risk.

Speaker 7

Okay, sounds good. That's great. All right. Yes, thanks for taking my questions and good luck in the months ahead.

Speaker 3

Thanks, Wayne.

Speaker 1

Thanks, Wayne. I've got a question online from Ovais Habib, our analyst at Scotiabank. Ovais says, cash costs in the first half have been below the guidance How should we look at the second half? Are you on track to beat the cash cost guidance or is there a catch up in costs and all in sustaining over the second half that we should expect?

Speaker 3

So I'll address the all in sustaining first. As you know, I think it's in the same line of questioning that Anita mentioned. Some of the sustaining capital was deferred into the second half of the year. We do intend to spend that. So you'll see an increase there on a per unit basis.

Speaker 3

With respect to cash costs as well, we do think they'll go up some as the inventory releases From the buildups, especially when related to our leaching operations. So we see those going up a little. And I'll just reiterate, if we hit around the top end of our guidance, then we will come in, we believe, right around the low end of both our cash Cost and sustaining all in sustaining cost guidance.

Speaker 1

Thank you. Operator, you can take the next question from the phone, please.

Operator

Thank you. The next question is from Dalton Baretto with Canaccord Genuity. Please go ahead.

Speaker 8

Thanks. Good morning, guys. You sound good considering the hour there. A few questions from me. Just first off on liquidity.

Speaker 8

Outside of your I-eighty stake, are you kind of happy with the existing liquidity you have right now relative to the remaining spend? Or are you going to look to Could that bolster it a little bit?

Speaker 3

Yes, outside of I-eighty, we're relatively happy. So and We don't see ourselves bolstering it.

Speaker 8

Okay, great. And then just On the 40% Orion stake in Greenstone, I know you can't speak to their intentions, but on the chance that they look to offload their stake kind of post commercial production. Do you guys have a ROFR on that stake? And then have you given any thought to how you would fund that?

Speaker 2

Yes, we have a ROFR. I think it's fair to say that we'd love to own more of Greenstone. And have we given any thought to how we fund it? I mean, not it's definitely nothing that I would call advanced. It's on our radar for sure, because at some point we expect we're going to need to act if we don't do something Preemptive, but absolutely, it's something we think about, it's something we talk to them about.

Speaker 2

And absolutely, we'd like to own more of Greenstone. How that ends up playing out, Dalton, I couldn't speak to that right now.

Speaker 8

Okay, thanks. And then Once Greenstone is in commercial production, how are you thinking about the broader portfolio? Are you kind of happy with it right now? Are you going to look to make some changes?

Speaker 2

I guess I'd say something I think I've said in the past, which is over the course of building the company, we've acquired mines, we've developed mines and we sold To mines, we're always looking to up tier the portfolio. And so if we can get to a place where we've got Larger, longer life mines that fill out our production profile. That's a goal that we aspire to. So I think we've got a lot of upside in our portfolio that we want to surface. And but that's not To say that we wouldn't make changes in the future.

Speaker 2

Right now, we're very focused on getting Greenstone built up and running and in commercial production. And then we've got a little more flexibility around the longer term strategy at that point. At this stage, we just want to keep our eye on the ball there at Greenstone.

Speaker 8

Thanks. And maybe just one last one. On Castle Mountain Phase 2, it sounds like you've got an initial response The BLM and they look like they're going to perhaps accept the application. Have they flagged any Kind of, let's call them, high risk areas that they'll be looking at? Or is this going to be reasonably straightforward?

Speaker 4

Well, both The county and BLM had a period where they can do their, I think it's called Assessment of completeness of our application and they made additional inquiries. So we responded and it's just in the overall Permitting process. So there's no indication of anything other than we've moved to the point of answering the questions to be complete, be able to enter fully into the rest of the process.

Speaker 8

So at this point in time, there's no kind of indications as to what they're going to be focused on, where they're going Look to actually mitigate certain things, water, that sort of thing?

Speaker 2

It looks really straightforward, Dalton, at this stage. It's an already operating mine. We're not expanding beyond the currently permitted EIS footprint that's already there. And we're not meaningfully changing the processing that was there previously. So it's a straightforward application.

Speaker 2

I guess the most painful part to us is just time, right? It's got to go through their process. I wish this permit was coming in, in 2024. Like it's going to be 2025. But no, we haven't received any comments that I would characterize as Controversial or concerning to us.

Speaker 8

Great. Thanks, guys. That's all for me.

Speaker 1

All right. We've got no further questions. If anybody thinks of anything after having a couple of cups of coffee, please do get in touch by email. Greg, do you have any closing remarks?

Speaker 2

No, just thanks everyone for joining the call so early today. I promise it's not something we're going to make a habit of. We had to accommodate some schedules, but I do appreciate those that got up early and attended the call. And thanks again for joining. As Raline said, you can always reach out to us directly and we're happy to answer questions.

Speaker 1

Okay. Thank you. Gail, you can close the call.

Operator

Thank you. This concludes today's conference call. You may disconnect your lines. Thank you for participating and have a pleasant day.

Key Takeaways

  • Record first-half sales of 261,000 ounces, including 138,000 oz in Q2 at cash costs of $13.61/oz and AISC of $15.02/oz, keeping 2023 production and cost guidance on track.
  • Greenstone project is 85% complete, remains on budget and schedule for first gold pour in H1 2024, with $170 M of capex remaining and over $300 M of liquidity secured.
  • Feasibility study for an underground expansion at Aurizona is progressing, targeting completion next year and potential to add a long-life underground operation alongside the open pit.
  • A fatality at the Santa Luz mine in June led to a one-week suspension and enhanced safety training; Q2 plant recovery averaged 67% with a 70%+ recovery target for H2 2023.
  • Q2 generated $81 M in operating cash flow (before working capital) and net income of $5 M, ending the quarter with $174 M cash and $127 M available on the credit facility.