Jesse Barrientez, aka Red Feather, center, plays the drums and sings tribal songs with other Indigenous people during a march, on Monday, June 7, 2021, in Clearwater County, Minn. More than 2,000 Indigenous leaders and "water protectors" gathered in Clearwater County from around the country to protest the construction of Enbridge Line 3. The day started with a prayer circle and moved on to a march to the Mississippi headwaters where the oil pipeline is proposed to be built. (Alex Kormann/Star Tribune via AP) Activist Jane Fonda joins hundreds of protesters chanting "Stop Line 3!" and "Water is life!" gathered at the headwaters of the Mississippi River in in Solway, Minn., on Monday, June 7, 2021 to resist a Canadian-based company's plan to replace an aging pipeline that carries crude oil from Alberta to Wisconsin. (AP Photo by David Kolpack) Activists lock arms as they occupy an Enbridge Line 3 pump station near Park Rapids, Minn., on Monday, June 7, 2021, as State Troopers, in background, direct traffic on Highway 71. (Evan Frost/Minnesota Public Radio via AP) A makeshift "black snake" resembling a pipeline is carried as demonstrators march along Highway 9, on Monday, June 7, 2021, in Clearwater County, Minn. More than 2,000 Indigenous leaders and "water protectors" gathered in Clearwater County from around the country to protest the construction of Enbridge Line 3. The day started with a prayer circle and moved on to a march to the Mississippi headwaters where the oil pipeline is proposed to be built. (Alex Kormann/Star Tribune via AP) A Customs and Border Protection helicopter descends near activists by an Enbridge Line 3 pump station near Park Rapids, Minn., on Monday, June 7, 2021. (Evan Frost/Minnesota Public Radio via AP) Activists are walked through an Enbridge Line 3 pump station after being arrested near Park Rapids, Minn., on Monday, June 7, 2021. (Evan Frost/Minnesota Public Radio via AP) An activist uses an umbrella for shade while sitting locked to an excavator at an Enbridge Line 3 pump station near Park Rapids, Minn., on Monday, June 7, 2021. (Evan Frost/Minnesota Public Radio via AP) Authorities from multiple law enforcement agencies secure the inside of an Enbridge Line 3 pump station from activists, near Park Rapids, Minn., Monday, June 7, 2021. (Evan Frost/Minnesota Public Radio via AP) Law enforcement agents form a line in front of a wall of protesters who sit just in front of a locked gate at an Enbridge pump station, Monday, June 7, 2021, in Hubbard County, Minn. Indigenous protesters and allies occupied the active site, some physically chaining themselves to equipment, forcing workers to leave, in protest of the construction of Enbridge Line 3. (Alex Kormann/Star Tribune via AP) Indigenous leaders and "water protectors" march through swamp land to the boardwalk leading to an Enbridge pipeline construction site, on Monday, June 7, 2021, in Clearwater County, Minn. More than 2,000 Indigenous leaders and "water protectors" gathered in Clearwater County from around the country to protest the construction of Enbridge Line 3. The day started with a prayer circle and moved on to a march to the Mississippi headwaters where the oil pipeline is proposed to be built. (Alex Kormann/Star Tribune via AP) Everlasting Wind, aka Dawn Goodwin, joins others by raising her fist in the Mississippi River near an Enbridge pipeline construction site, on Monday, June 7, 2021, in Clearwater County, Minn., to protest the construction of Enbridge Line 3. Goodwin is a co-founder of RISE Coalition. More than 2,000 Indigenous leaders and "water protectors" gathered in Clearwater County from around the country. The day started with a prayer circle and moved on to a march to the Mississippi headwaters where the oil pipeline is proposed to be built. (Alex Kormann/Star Tribune via AP) Faith leaders gather for an interfaith prayer gathering before a day of protest action against the Enbridge Line 3 oil pipeline at LaSalle Lake State Recreation Area on Monday, June 7, 2021. (Evan Frost/Minnesota Public Radio via AP)
ST. PAUL, Minn. (AP) — The Minnesota Court of Appeals on Monday affirmed state regulators' key approvals of Enbridge Energy’s Line 3 oil pipeline replacement project, in a dispute that drew over 1,000 protesters to northern Minnesota last week.
A three-judge panel ruled 2-1 that the state’s independent Public Utilities Commission correctly granted Enbridge the certificate of need and route permit that the Canadian-based company needed to begin construction on the 337-mile (542-kilometer) Minnesota segment of a larger project to replace a 1960s-era crude oil pipeline that has deteriorated and can run at only half capacity.
Pipeline opponents said they are considering an appeal to the Minnesota Supreme Court, but that their main focus is trying to persuade President Joe Biden to intervene and the continuing protests. The Biden administration hasn't taken a clear position on Line 3, but a legal challenge is pending in federal court on the U.S. Army Corps of Engineers' approval of a wetlands permit that activists say should be withdrawn.
Tribal and climate change groups, plus the state Department of Commerce, had asked the appeals court to reject the approvals. They argued that Enbridge’s oil demand projections failed to meet the legal requirements. But the court said there was reasonable evidence to support the PUC's decision.
“With an existing, deteriorating pipeline carrying crude oil through Minnesota, there was no option without environmental consequences,” wrote Judge Lucinda Jesson, joined by Judge Michael Kirk. “The challenge: to balance those harms. There was no option without impacts on the rights of Indigenous peoples. The challenge: to alleviate those harms to the extent possible. And there was no crystal ball to forecast demand for crude oil in this ever-changing environment."
But Judge Peter Reyes dissented, agreeing with opponents that the oil demand forecast was flawed. He said the project benefits Canadian oil producers but would have negative consequences for the hunting, fishing, and other rights of the Red Lake and White Earth tribes, and would provide no benefit to Minnesota.
“Such a decision cannot stand. Enbridge needs Minnesota for its new pipeline," Reyes wrote. "But Enbridge has not shown that Minnesota needs the pipeline.”
Tribal and environmental groups welcomed Reyes' dissent and vowed to keep fighting. They said their primary strategy going forward won't hinge on appeals, given they could take nine months to a year. Enbridge hopes to put the line into service in the fourth quarter.
“There's a good chance we'll appeal because we should ... but I don't think a remedy's going to come out of it that's going to be meaningful for us,” said Frank Bibeau, an attorney for the White Earth Band of Ojibwe and other pipeline opponents.
Enbridge said in a statement that the court's decision is confirmation that the commission thoroughly reviewed the project and gave the appropriate approvals.
“Line 3 has passed every test through six years of regulatory and permitting review, including 70 public comment meetings, appellate review and reaffirmation of a 13,500-page (environmental impact statement), four separate reviews by administrative law judges, 320 route modifications in response to stakeholder input, and multiple reviews and approvals by the Minnesota Public Utilities Commission for the project’s certificate of need and route permit."
At least 1,000 activists from across the country gathered at construction sites near the headwaters of the Mississippi River last week. They urged Biden to cancel the project, as he did the Keystone XL pipeline on his first day in office. Nearly 250 people were arrested, in addition to more than 250 arrests since construction began in December. A smaller group marched Thursday to the Minneapolis office of Democratic Sen. Amy Klobuchar.
The Line 3 replacement would carry Canadian tar sands oil and regular crude from Alberta to Enbridge's terminal in Superior, Wisconsin. The project is nearly done except for the Minnesota leg, which is about 60% complete.
Opponents of the more than $7 billion project say the heavy oil would accelerate climate change and risk spills in areas where Native Americans harvest wild rice, hunt, fish, gather medicinal plants and claim treaty rights.
Enbridge says the replacement Line 3 will be made of stronger steel and will better protect the environment while restoring its capacity to carry oil and ensure reliable deliveries to U.S. refineries.
Activists are vowing to keep up a summer of resistance against the project amid the escalating battle over energy projects and rising awareness that racial minorities suffer disproportionate harm from environmental damage. And they're drawing parallels with the fight over the Dakota Access pipeline, which was the subject of major protests near the Standing Rock Reservation in the Dakotas in 2016 and 2017.
“Our resistance is clearly growing. We cannot stop and we will not stop,” said Tara Houska, founder of the Giniw Collective, one of the Indigenous groups behind last week's protests.
Before you make your next trade, you'll want to hear this.
MarketBeat keeps track of Wall Street's top-rated and best performing research analysts and the stocks they recommend to their clients on a daily basis.
Our team has identified the five stocks that top analysts are quietly whispering to their clients to buy now before the broader market catches on... and none of the big name stocks were on the list.
They believe these five stocks are the five best companies for investors to buy now...
See The Five Stocks Here
Thinking about investing in Meta, Roblox, or Unity? Click the link to learn what streetwise investors need to know about the metaverse and public markets before making an investment.
Get This Free Report