Torex Gold Resources Q3 2023 Earnings Call Transcript

There are 7 speakers on the call.

Operator

Welcome to Torex Gold's Third Quarter 2023 Conference Call and Webcast. As a reminder, all participants are in listen only mode and the conference is being recorded. After the presentation, there will be an opportunity to ask Call. I would now like to turn the conference over to Dan Rollins, Senior Vice President, Corporate Development and Investor Relations. Please go ahead.

Speaker 1

Thank you, operator, and good morning, everyone. On behalf of the Torex team, welcome to our Q3 2023 conference call. Before we begin, I wish to inform listeners that a presentation accompanying today's This call can be found under the Investors section of our website at www.torrexgold.com. I'd also like to note that certain statements to be made today by the management team may contain forward looking information. As such, Please refer to the detailed cautionary notes on Page 2 of today's presentation as well as those included in the Q3 2023 MD and A.

Speaker 1

On the call today, we have Jody Kosanko, President and CEO Andrew Snowden, CFO as well as Dave Stephanuto, Executive Vice President, Technical Services and Capital Projects. Following the presentation, Jody, Andrew and Dave will be available for the question and answer period. This conference call is being webcast and will be available for replay on our website. Last night's press release and the accompanying financial statements and MD and A are posted on our website and have been filed on SEDAR. Also note that all amounts mentioned in this call are U.

Speaker 1

S. Dollars unless otherwise stated. I'll now turn the call over to Jody.

Speaker 2

Thank you, Dan, and good morning to all on the line. Welcome to the Torex Gold Q3 2023 results call. I'll open my remarks by saying that while the Q3 was challenging on a number of fronts, it's behind us and we're well on track to achieve full year production guidance for the 5th year in a row. We produced 85,000 ounces in Q3. Now partway into Q4, open pit grades are picking back up as expected.

Speaker 2

October production came in at 41,500 ounces and that is with a planned 100 5 hour plant maintenance shutdown to start off the month. We're now through the high strip low grade phase of the open pit mine plan and expect more consistent production moving forward. As we announced at the end of October, Medi Luna is advancing to plan and remains on track for first production in late with breakthrough of the scheduled critical Wajes tunnel on track for late December, a full 3 months ahead of plan. In addition, drilling on both sides of the river continues to demonstrate the resource potential of the property, and we'll have more updates on the drilling over the coming weeks. Opening highlights for this quarter's call include: 1st, ounce production was impacted by the sequencing of the open pits, which saw us rely heavily on lower grade Stockpiled ore and lower grade run of mine ore.

Speaker 2

The impact of the lower grade feed was partially offset by Same performance excellence on throughput and recoveries in the mill as well as another new quarterly record on mining rates in the ELG underground. Total cash cost guidance and all in sustaining cost guidance has been revised higher, with about half of the increase reflecting the ongoing strength of the Mexican peso and the other half, the combination of the higher mines and processed volumes. We were moving a lot of material to help offset some of the lower process grades during Q2 and Q3. We've also revised 2023 full year CapEx Guidance on Medialuna to reflect the spend we have achieved year to date. This should come as no surprise.

Speaker 2

We've been talking about it since early in the year. And notably on Medialuna, just late yesterday, we received our final permit for the in pit tailings deposition at Juarez, which means that we are now fully permitted to start operations. So this is a significant de risking milestone for us. In terms of the agenda for the call, it's the usual I'll provide a brief reminder on the strategic pillars, which continue to frame our execution plans. Then I'll step you through the key business operational highlights specific to the Q3, then over to Andrew Snowden on The financials have been Dave Stefanuto on Medialuna.

Speaker 2

I'll make some closing remarks and then hand the call over to the operator for Q and A. Starting on Slide 4 with a review of our strategic pillars, which set up the long term vision of Torex, the strategy remains unchanged. You can see on this slide the 5 key areas of focus that frame up our work as we make our way to the finish line in 2023. 1st, On Optimize and Extend ELG, drilling at the ELG underground continues to demonstrate the potential to replace reserves and grow resources, which in turn provides us with confidence in our ability to extend the life of that mine well beyond 2026. On derisk and advanced Medi Luna, with 15 months left in the project, we're sitting at about the halfway mark on completion.

Speaker 2

Underground Development and Construction is tracking to plan and we made some solid progress on the engineering front in the quarter, which should in turn supports increased procurement activity over the coming months. Surface construction is now picking up pace with concrete being poured across multiple work areas and steel erection on the flotation plant on track for year end. On grow reserves and resources, drilling at EPO highlighted the potential to Upgrade additional inferred resources to the indicated category, which will support initial mine planning and an internal economic assessment next year, which, if positive, We expect to pave the way for another new mining front on the south side of the river. We have a few exploration releases in the queue, so you can expect to see some additional news on this front over the next 3 months. On the Pillar of Trinity Capital Management, we closed the quarter with available liquidity of $501,000,000 This is compared to the $506,000,000 remaining to be spent on the Medialuna build.

Speaker 2

This strong balance sheet combined with another 15 months of free cash We closed the quarter with a lost time injury frequency of 0.47 with no lost time injuries during the quarter. Post quarter end, the ELG operation, this is employees and contractors now, surpassed 10,000,000 hours lost time entry free to the 3rd time since 2020. I know I'm personally pretty proud of that one. I know the team is as well. There are very few minds that achieved this milestone once, let alone 3 times in the span of 4 years.

Speaker 2

Turning to slide 5. Despite the fact that the operations are running very well, we produced 85,000 ounces The quarter, which places us at 316,000 ounces through the end of Q3 against full year guidance of 440 to 470. We remain on track to achieve full year production guidance with Q4 expected to be the strongest quarter of the year, driven by grade coming back up in pit as we're now in the higher grade benches at the pushback. With the stripping quarters behind us and grade coming back up, we'll just keep doing what we're doing with consistent throughput from the plant and consistent performance from the ELG underground and bring this year home as planned. On costs, due to the impact of the stronger At Can Peso, the focus on waste stripping and the lower ounce denominator, both total cash costs and all in sustaining costs were elevated during the quarter.

Speaker 2

With the period of heavy stripping now behind us and improved open pit grades, costs are expected to materially improve in Q4, just not enough to get us back in line with original guidance. Cash flow from operations was $44,000,000 impacted by the lower gold sold during the quarter as well as the higher proportion of waste stripping expensed versus capitalized. We expect a material pickup in operating cash flow in Q4 driven by the strongest quarter of the year production wise, lower costs and continued gold price strength. With a spending of $99,000,000 on the Medi Luna project during the quarter, we closed the quarter with $209,000,000 of cash on hand and available liquidity of $501,000,000 Turning now to some operational highlights on Slide 6. You can see there on the top left that shows the quarterly production I've already discussed.

Speaker 2

Top right demonstrates the steady performance of the process plant. TruPoint has surpassed 13,000 tonnes per day for the last three quarters and we expect a similar level of performance in Q4. Bottom left, you can see the quarterly dip in grade reflected on the chart, which is now behind us. And finally, on the bottom right, we set another record in the ELG underground with Average mining rates in excess of 2,300 tons per day. We'll keep the foot on the gas here in Q4 before Pulling back on rates in 2024, on this point, I would note that 2,000 tonnes per day in that range is an optimal level for that underground asset based on current reserves.

Speaker 2

Moving to Slide 7, which is the overview of our annual guidance. We're on track to achieve full year production guidance. Open pit grades are picking up as As noted earlier, total cash cost guidance is up $95 an ounce The only other change to CapEx is at Medialuna, where we're now anticipating spending between $360,000,000 $390,000,000 this year versus the original guidance of $3.90 to $4.20 We had noted that spending was tracking towards the low end of the guided range in the October Medi Luna update. So the update here really just reflects spending through the 1st 9 months of the year. I want to emphasize that the lower spend in 2023 doesn't have any impact on the project schedule and Dave will step you through this in some detail later in the presentation.

Speaker 2

On to some exploration news on Slide 8 in July, we provided an update on the ELG underground, which continues to reinforce Confidence in extending the reserve life of that asset well beyond 2026. Our understanding of the structural controls of the deposit continues to be refined specifically around that north northwest trending corridor. We're putting the file touches on another ELG underground results release and expect to publish that in the coming days. A bit of a spoiler alert here, there are some very nice holes in there that continue to reinforce our confidence for the long term Moving now to Slide 9. The success on the north side continues to be replicated on the south side of the Balsas This river was drilling at EPO delivering 2 key findings.

Speaker 2

1st, infill drilling along the southern portion of the deposit has demonstrated similar grades and width as previous drilling, which bodes pretty well for our ability to upgrade additional inferred resources to the indicated category. And second, Stepo Drilling to the North has confirmed mineralization 500 meters to the North, noting the potential for higher EPO remains a key focus for our geology and technical teams given the underlying resource potential to both The north and the south of the deposit as well as the potential to become a future source of mill feed from the south side of the property. Next steps at EPO are to deliver an updated resource at year end. This resource will form the basis for some mine planning work, which will in turn form the basis for an internal economic study. Given the proximity of EPOs, the Medialuna infrastructure and what we can clearly see as the mineral endowment, we're quite eager to see these results.

Speaker 2

We expect to have a couple of more exploration releases out on the Southside drilling activity over the next few months. First up is expected to be a release on our initial drill program at Medialuna West and subsequent to that, our final results from the drilling this year at EPO. With that, I'll pass the call over to Andrew to take you through the financial performance and the balance sheet.

Speaker 3

Okay. Thank you, Jody, and good morning, everyone. Starting first on Slide 11, our financial performance in Q3 reflects the lower production and sales volumes achieved during the quarter as well as the tail end of the high stripping phase in the open pit. Just to emphasize, as Jodi noted in her remarks, our financial performance is expected to materially improve in Q4, driven by the strongest production quarter of the year And materially stronger margins given the anticipated improved cost performance and continued strength of the gold price. Our financial performance in 2023 to date has also been impacted by the ongoing strength of the Mexican peso, which has averaged $17.8 to 1 relative to the U.

Speaker 3

S. Dollar in the year and that's compared to our planning and guidance, which assumed a rate of 20 to 1. You'll recall for every one peso move relative to the U. S. Dollar, our all in sustaining costs are impacted by approximately $10,000,000 which year to date has added about $50 an ounce to both total cash costs and all in sustaining costs.

Speaker 3

These grade and foreign exchange factors combined have resulted in Q3 total cash costs of $10.86 an ounce, All in sustaining costs of $14.50 an ounce and adjusted EBITDA of $61,000,000 Finally, on this slide, just looking at free cash flow, which is shown in the bottom right quadrant. We reported a $70,000,000 deficit during the quarter, reflecting the lower operational performance and the highest spending on Media Luna, which increased $22,000,000 quarter over quarter to 99,000,000 We expect spending on Media Luna to increase again in Q4 as surface and underground construction continues to progress. Turning now to Slide 12, you can see here a summary of our unit cost performance. Despite the ongoing pressure from the stronger Mexican peso, Mining costs are tracking well and in line with costs achieved in 2022. In the open pit, improved And at ELG underground, the continued economies of scale from record mining rates achieved have led to the stronger cost performance you see here year to date.

Speaker 3

At the processing plant, the increased costs relative to 2022 reflects primarily the higher consumable prices, which we flagged at the start of the year as well as the stronger Mexican peso and that's been partially offset by the higher mill throughput we've seen year to date. Turning now to Slide 13, you can see here the $70,000,000 in negative free cash flow in the quarter Resulted in an expected decrease in our cash balance to $209,000,000 as of September 30. The key drivers you can see in the waterfall here of its use of cash were primarily the capital expenditures, where we invested 100 and $12,000,000 during the quarter, reflecting the increased spending on Media Luna of $99,000,000 and that Media Luna spend was partially offset by Adjustment of $14,000,000 which reflects invoices accrued versus paid during the quarter. Also just to point out quarterly tax payments were $12,000,000 in Q3 and that's below the $6,000,000 to $7,000,000 of monthly tax installments We anticipated in the year and that's really just given the lower taxable income we saw in Q3. I do The monthly tax installment in Q4 to remain at these levels and that's because the higher taxable income we expect in Q4 will be partly Based on the level of spending on Media Luna over the next 15 months, we expect free cash flow to remain negative through to the end of 2024 Before improving in 2025 with the ramp up of Media Luna and the material decline in capital expenditures.

Speaker 3

Turning next to Slide 14, you can see here that despite the increased capital spending in Q3, our balance sheet remains strong, Continuing to position us well to fully fund Media Luna. We closed out the quarter with $209,000,000 in cash, A further $292,000,000 of available capacity on our credit facilities and so a total of $501,000,000 in available liquidity. You'll also note our lease obligations have increased during the quarter to $21,000,000 as further advanced payments were made by our lessor to the Media Luna mobile equipment suppliers. We started to receive some of this equipment in Q4. As demonstrated next on Slide 15, You can see how this liquidity well supports the remaining forecast capital expenditure on Media Luna, while also supporting our broader strategy to invest meaningfully in exploration and drilling, while maintaining a strong balance sheet during the build period.

Speaker 3

We now estimate only $106,000,000 of cash flow generation is required from ELG over the next 15 months to fund our strategic objectives And that includes the $508,000,000 remaining on Media Luna as well as our strategic goal of maintaining at least $100,000,000 on the balance sheet. This internal cash flow requirement compares with $184,000,000 of free cash flow generated prior to spending on the Media Luna project over the last 12 months and this includes Q3, which in our view does not reflect the true cash flow generation of the ELG operations. If you extrapolate this last 12 months free cash flow from ELG over the remaining 15 months project period, It implies $230,000,000 of cash generated from the existing operations compared to the $106,000,000 requirement. This is why we're confident on our ability to fund the remaining expenditures on Media Luna and fund the any cost pressures arising from the Mexican peso. Finally, now just an update on hedging, which you can see summarized here on Slide 16.

Speaker 3

There would be no change to the going forward contract With respect to both volumes or price through to the end of 2024, as we've noted in the past, we don't enter into gold hedges lightly. We thought it was prudent to execute these purpose built hedges to protect between 25% to 40% of quarterly production During a period where internal cash flow was a key source of funding for Media Luna. An area that where we have added protection is the mix of Can peso. We have now placed 0 cost collars on over $100,000,000 of future capital expenditure between October 2023 December 2024. These callers have an average peso floor price of $17,400,000 and an average ceiling of $20,000,000 Given the strength of the peso, we thought it to be prudent to try and minimize any further downside risk related to the peso given about 40% to 50% of the remaining project We're confident that our operating plans, the $875,000,000 of Media Luna Capital had assumed an average peso of 20 to 1.

Speaker 3

We will continue to evaluate foreign exchange markets and may consider some additional protection And with that, I'll hand the call over to Dave for an update on Media Luna.

Speaker 4

Thanks, Andrew. Slide 18 shows the progress at Media Luna after the 1st 18 months of the 33 month build period. The main takeaway is that at the halfway mark, the project is tracking the schedule and budget. Noting the ongoing strength of In peso and the general inflationary pressures are headwinds to continue to contend with. At quarter end, the project was 49% complete across procurement, engineering, underground construction development and surface construction, up from 35% at the start of the quarter.

Speaker 4

On the engineering front, significant headway was made as we leveraged additional resources to make up for the slow start of the year, which is expected to support procurements and contracting activities over the coming months. Steady progress was made on procurement with the first deliveries under the Sandvik Contract made in September. Overall progress was slightly lower than we had expected given several purchase orders and contract awards were pending finalization at the quarter end. Surface construction activities on the north side are expected to ramp up over the coming months as more concrete work fronts become available and steel erection On the sell side, completion of the Mazapa bypass road this quarter will allow for construction activities on the base plant Commence as the roads have been widened to support the delivery of large pieces of fixed equipment. Significant process Progress was also made with the underground development and construction driven by continued steady advance rates in the Guarez tunnel And the Southport Aloha as well as mobilization of Dumas, who has been awarded the underground construction and vertical development contract.

Speaker 4

As of today, we have 20 active headings within Media Luna and have completed over 19,000 meters of lateral and vertical development, representing 63% of the total development required. During the quarter, we invested $99,000,000 in the project, resulting in a remaining expenditure of $508,000,000 over the next 15 months. As of the quarter end, 68% of the upfront projects expenditures have been committed, including 42% incurred. Although the level of spending is expected to pick up in Q4, we have lowered our guided spend in 2023 by $30,000,000 The level of spend is expected to remain elevated through Q3 2024 before declining as the project nears completion and achieve commercial production in early 2025. The lower spend has no impact on project schedule given that the spend really reflects the decision To align the installation of the iron sulfide flotation circuit and water treatment plant with the installation of the remaining copper flotation circuit as well as some modest rescheduling of non critical elements.

Speaker 4

With respect to the iron sulfide flotation circuit and water treatment plant, The rescheduling reflects the reality that the business case for an early installation is no longer warranted given cyanide consumption levels have been stable at 2.5 kilograms per ton compared to the plus 5 kilograms per ton level experienced in 2021 when the schedule was initially defined. Moving on to Slide 19, we'll provide an update on the scheduled critical wide left at quarter end, we've officially pulled the breakthrough of the scheduled critical wires tunnel to late December. This is an amazing 3 months ahead of March 2024 breakthrough that was envisioned in the 2022 technical report. The progress north to south and south to north has truly been With an advanced combined rate, an average combined rate of advance of 11.2 meters per day over the last 3 months. From north to south, our home crews have averaged 7.5 meters per day, which is world class by any standards, Considering the size of the widest tunnel, which is 6.5 meters by 6 meters wide.

Speaker 4

The additional 3 months of schedule will provide ample time to install and commission 7 kilometer conveyor which will be hung in the tunnel. Anchoring and bolting for the 1,000 plus conveyor tables will commence shortly. All of the conveyor tables are now at site and are over half as is over half of the belt segments with the remainder in transit. On Slide 20 are some recent pictures from the site. The top left picture is a picture of a sunset of the flotation plant, which is really coming together.

Speaker 4

With the installation of the tower crane, we expect to begin steel erection by year end. In the top center, we see the foundations progressing for The water treatment plant in the foreground and foundation work starting in the back for the new 230 kilobytes substation. To the right, the mass Earthworks fill is underway in the location of the new copper concentrate storage and blending building. The lower left picture is the new Mazapa bridge abutments Ready to receive the precast concrete beams and bridge deck, which will allow movement of larger loads and materials to Media Luna by year end. Finally, on the lower right, the medium voltage and fiber optic overhead distribution lines were relocated into buried conduits And successfully energized allowing the flotation plant construction to proceed.

Speaker 4

And with that, I'll now turn it over to Jody.

Speaker 2

Great. Thanks, Dave. Overall, my closing comments are this. We have a challenging 5 months behind us. We're well on track to close out 2023 on a solid note and one which will demonstrate the operational and financial performance our shareholders have come to expect of us.

Speaker 2

We plan to carry the strong Q4 performance and momentum into 2024, which will be a big year for the company as we complete Medialuna, as we finalize an internal economic assessment on EPO, as we continue to unlock the resource potential of the broader Miraldos property with ongoing exploration and critically from my perspective as we make our way back to cash flow in 2025. With that, I'll pass the call over to the operator for the Q and A period.

Operator

Thank you. We will now begin the question and answer session. Our first question comes from Don DeMarco of National Bank Financial. Please go ahead.

Speaker 5

Thank you, operator, and good morning, Jody and team. Congratulations on getting through this tough period and also Encouraged by the strong results in October. So maybe my first question starts with that. You mentioned that you got an average process Great. A 4 grams per tonne in October.

Speaker 5

And what can we expect for the rest of the year and into Q1 on grades? Certainly, you got a lot of momentum and looking at a strong Q4, but do we expect that momentum to continue into Q1?

Speaker 2

Yes. Thanks, John. And, yes, you've talked about months behind us. The short answer to your question is we expect grades to return to around 4 gram ton. We're into the really dense and greasy parts of the deposit at 83 and that open pit pushback and we plan to be mining that through Q4 and into 2024.

Speaker 2

So momentum will continue. We'll return to usual Torex quarter is here and are looking forward to it.

Speaker 5

Okay. So I see the technical report Calls for grades next year, I think just over 3 grams per tonne. So I think you mentioned that you expect these 4 grams per tonne to continue for a period of time. Does that suggest that production next year is going to be front end loaded, that Q1 will be heavier in order to kind of reach that 3 grams a ton average grade over the year?

Speaker 2

Production next year, we're looking at a fairly balanced profile. I would say the exception to that The plan has us taking a 4 week downtime at the process plant in October To do the tie ins and the motor changes and the installation of the VFDs in the Ball Mills to bring up Medialuna. The grade, we expect to be in the 4 gram There may be periods of time in there, Don, that it's 3 grams because recall next year we're mining from Eighty three in the open pit. We're going to continue to push ELG underground and we're drawing from stockpiles with a view to generating smooth production and cash flow as we've finished this transition between the open pits coming offline and Medialuna coming on at the back end of the year.

Speaker 5

Okay, that's great. So we see that the guidance was revised upward. I mean the new midpoint for ASIC is now 11.80 an ounce, Still very attractive relative to industry peers. But also referencing back to the technical report, we saw for 2023 it was $987,000 So there's about a $200 delta there. Of course, we know that the Mexican peso has weighed on a number of operators in Mexico.

Speaker 5

But is it fair that we should maybe in looking at our models adjust some of the ASIC or costs in 2024 or 2025 By up by similar margin as we saw in 2023?

Speaker 3

It's Andrew here, Don. So I'll take that. We'll come out with our full year 2024 cost guidance in January as we usually do so, but to provide more clarity On that to that point, I will just add though in terms of impact since the technical report was released In whenever it was March of 2021, Three wide factors including inflation, the Mexican peso that you referred to as well as some higher cyanide costs that we So those are factors that will put some upward pressure on ASIC. That said, I do Expect that ASIC will decline in 2024 versus what we've experienced here in 2023. Of course, as Joni has mentioned, we're through the heavy stripping phase Of the pushback now in 2023, and so we'll see much less waste removal required through the course of 2024.

Speaker 3

And so you'll see I said kind of normalized more now through the course of 2024, but we'll be out in January with some more specific guidance on that.

Speaker 5

Okay. Yes, great. Well, thanks for that color. Then we'll recalibrate our estimates with those factors in mind as we await that guidance in Q1. Now you've got about $500,000,000 left in CapEx to spend and you may have covered this, but what are you thinking about Impacts from the Mexican peso or potential inflation on that number, are you still pretty comfortable with that number?

Speaker 5

Or do you think there's those factors are maybe

Speaker 3

We're still comfortable with the number, Don. I mean, clearly, the Mexican peso is putting pressure on our Cash expenditure across the board, both operational and capital. I've talked before about at least as it relates to Media Luna, A one peso impact or 1 peso movement in the exchange rate has about a $15,000,000 impact on Total project costs. And so as you kind of look at year to date, we've had a rate of, let's just call it, 18 to 1 versus 20. And so over the life of the project, if that was to continue throughout the life of the project, that puts about a $30,000,000 pressure On capital, we are of course looking for opportunities as we execute on the project to try and find offsets for that $30,000,000 but that's where we are seeing Some pressure.

Speaker 5

Okay, great. Well, that's all for me. Thank you for that and Good luck with the rest of Q4 and congratulations also on the favorable Semrinac decision that just came out this morning. Thank you.

Speaker 2

Thanks, Don. We're pretty excited about being fully permitted.

Operator

Our next question comes from Eric Windmill of Scotiabank. Please go ahead.

Speaker 6

Great. Good morning, Jody and the team. Thanks for taking my question. Just a question on the cyanide consumption, obviously, came down in the quarter. Any additional clarity on that?

Speaker 6

Is it all sort of just ore feed related or the other measures contributing to that decrease in the cost?

Speaker 2

Yes, I'll take that one, Eric. There are a number of measures that relate to cyanide consumption improving quite materially over the course of the last year. So number 1 is We have different feed mixes with different levels of soluble copper and soluble iron. Soluble iron is the primary consumer of our cyanide. And so as we moved out of Wajes And then to El Limon more specifically through the middle of this year that helps.

Speaker 2

Number 2, we have a very disciplined blending program that just keeps getting better and Better to control the feed inputs to the plant, what you don't want are the peaks in soluble copper so that you overdose and waste The cyanide, so if you saw our run charts, our SPC charts, we run very smoothly that way. Number 3, We've installed some technology called the mock reactor in our, leaking circuit. And what it essentially does is it blows bubbles into the solution to help rust out some of that iron instead of it consuming the cyanide. So those three things have really And then the other really relevant factor for us is margin. And we've been able to negotiate some fairly aggressive contracts for unit rates on cyanide that we're pretty pleased with and we're going to continue to push on our suppliers to get even better rates through next year.

Speaker 6

Okay, great. No, that's super helpful. Thank you. Maybe just one more for me. Obviously, great to see the permit here for the in pit tailings.

Speaker 6

Any comments here? I know you're doing work to prepare for that next year in terms of like critical path items before you can

Speaker 4

Yes, absolutely. In terms of the actual work to Start deposition. This is Dave Stefnuto here. To start the input deposition in the Duarte's pit, we do need to prepare the floor of the pit. The preparation is actually quite simple.

Speaker 4

We've already installed our downstream monitoring wells that we'll use post Starting the deposition to monitor any potential seepage and groundwater quality issues. So that work is actually already completed. So the next stage is really installing a drainage system at the base of the Guarez pits and a pump back And so we're scheduled to do that probably starting around mid next year. It's actually quite simple work. And then there'll be a discharge line for the actual input tailing system to put in place.

Speaker 4

So we're well positioned. We weren't anticipating originally in the FS to get the permit this early. So we've got quite a bit of time now to do this final installation.

Speaker 6

Okay, great. Thank you. Appreciate that. And I guess should we assume then, are you intending to decommission All the dry stack or you'll obviously continue to sort of run both concurrently at the outset?

Speaker 4

No, the intent is that we will stop the dry stack. We will not Fully decommission it. There's no rush to do that. However, once we do transition to the Guadis infant tailing system, We cannot readily go back to filter tailing without expending some capital to change our facility to do so. So really that can become a provision in the future should we ever have to go back to filter tailings, we will be able to do that, but now it's a little bit of work On the infrastructure to facilitate that.

Speaker 4

So really our plan is once we start Media Luna, we will start input deposition with 50% of tailings going to the Guaras pit and then the other 50% will be deposited as part of our paste backfill underground in the mine.

Speaker 6

Okay, thanks. No, I appreciate that. Really appreciate the added color. I'll hop back in the queue. Cheers.

Operator

As there appear to be no more questions, this concludes today's conference call. You may disconnect your lines. Thank you for participating and have a pleasant day.

Key Takeaways

  • Q3 production of 85,000 oz was softened by lower‐grade stockpiled and run‐of‐mine ore, but October output rebounded to 41,500 oz at about 4 g/t, keeping full‐year guidance on track.
  • Cost guidance was raised as all-in sustaining costs climbed to about US$1,450/oz, driven half by a stronger Mexican peso and half by higher waste stripping, though Q4 costs are expected to materially improve.
  • Medi Luna is 49% complete and remains on schedule and budget, with the critical Wajes tunnel breakthrough now penciled in for December—three months ahead of plan—and final in-pit tailings permits secured.
  • Balance sheet liquidity stands at US$501 m (US$209 m cash plus US$292 m undrawn facilities), and only US$106 m of free cash flow from ELG is needed to fund the remaining US$508 m of Medi Luna CapEx.
  • Exploration continues to deliver as infill and step‐out drilling at the ELG underground and EPO zones confirm grade and width, underpinning reserve extensions and a year-end resource update.
AI Generated. May Contain Errors.
Earnings Conference Call
Torex Gold Resources Q3 2023
00:00 / 00:00