At QB, reflecting the slower ramp up this year, we have narrowed our QB production guidance to 200,000 to 210,000 tonnes to 2024 from 200,000 to 235,000 tonnes. Further, we've revised our 2025 production guidance range for QB to 240,000 to 280,000 tonnes from 280,000 to 310,000 tonnes, reflecting planned activities to improve copper recovery and equipment reliability scheduled to run through the first half of twenty twenty five. Full year production at Highland Valley is now expected to be between 97,000 to 105,000 tons from 112,000 to 125,000 tons due to the delay in accessing the higher grade Launex pit in Q3. For molybdenum, our production guidance is reduced to 3000 to 4000 tons from 4,300 to 5,500 tons in line with the changes to our copper production guidance. We have reduced our QB molybdenum production guidance to 0.8,000 to 1,200,000 tons for 2024 and to 4,000 to 5,500 tons for 2025, from 1,800,000 to 2,400 tons and 5,000 to 6,400 tons, respectively.