Dundee Precious Metals Q3 2026 Earnings Call Transcript

Key Takeaways

  • Positive Sentiment: DPM reported strong third-quarter results, including $179 million in free cash flow, $144 million in adjusted net earnings, and revenue up 17% year over year. It returned $81 million to shareholders and ended the quarter with $839 million in cash, no debt, and $1.2 billion in total liquidity.
  • Positive Sentiment: Production was approximately 96,000 gold-equivalent ounces, keeping DPM on track to meet 2026 production guidance for the 12th consecutive year. Vareš reached commercial production ahead of schedule, is targeting its 850,000-ton annualized run rate by year-end, and is expected to exceed the high end of its 2026 production guidance.
  • Positive Sentiment: DPM advanced its growth pipeline: Block 250 is being incorporated into the Chelopech mine plan, with first production targeted for late 2028, while drilling at Brevene Porphyry South continues ahead of a planned initial resource estimate in the second half of 2027. Expanded drilling at Čoka Rakita also indicates potential to grow the resource.
  • Negative Sentiment: Regulatory uncertainty could affect project timing: Bosnia and Herzegovina’s Constitutional Court ordered a six-month review of acts related to the Vareš concession, although the company said operations continue normally and the decision does not suspend the concession. In Serbia, government formation after the October election may extend administrative and regulatory timelines for Čoka Rakita.
AI Generated. May Contain Errors.
Earnings Conference Call
Dundee Precious Metals Q3 2026
00:00 / 00:00

Transcript Sections

Skip to Participants
Operator

Thank you for standing by, and welcome to DPM Metals Q3 2026 Earnings Conference Call. Currently, all participants are in a listen-only mode. After the speaker's presentation, there will be a question-and-answer session. To ask a question during the session, you will need to press star one one on your telephone. To remove yourself from the queue, you may press star one one again. I would now like to hand the call over to Jennifer Cameron. Please go ahead.

Jennifer Cameron
Jennifer Cameron
Director of Investor Relations at DPM Metals

Thank you, and good morning. Sorry for the slight delay in starting this morning, a couple of technical difficulties, but hopefully, like everyone's email, we're back on track. I'm Jennifer Cameron, Director of Investor Relations, and I'd like to welcome you to our third quarter conference call. Joining us today are members of our senior management team, including David Rae, President and CEO, and Navin Dyal, Chief Financial Officer. Before we begin, I'd like to remind you that all forward-looking information provided during this call is subject to the forward-looking qualification, which is detailed in our news release and incorporated in full for the purposes of today's call. Certain financial measures referred to during this call are not measures recognized under IFRS and are referred to as non-GAAP measures or ratios.

Jennifer Cameron
Jennifer Cameron
Director of Investor Relations at DPM Metals

These measures have no standardized meanings under IFRS and may not be comparable to similar measures presented by other companies. The definitions established and calculations performed by DPM are based on management's reasonable judgment and are consistently applied. These measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures prepared in accordance with IFRS. Please refer to the non-GAAP financial measures referred to in our most recent MD&A for reconciliations of these measures. Please note that unless otherwise stated, operational and financial information communicated during this call are related to continuing operations and have generally been rounded. References to 2025 pertain to the comparable periods in 2025, and references to averages are based on midpoint of our outlook or guidance. I'll now turn the call over to David Rae.

David Rae
David Rae
President and CEO at DPM Metals

Good morning, and thank you all for joining us. I want to start by recognizing the dedication of our teams across all operations, whose commitment to safety, operational excellence, and responsible mining continues to drive our success. We delivered strong results in the third quarter, generating robust free cash flow and earnings while continuing to advance our growth strategy. The achievement of commercial production at Vareš ahead of schedule and the continued advancement of our growth pipeline, including the expansion of Brevene Porphyry South discovery, have further demonstrated DPM's position as a growing European-focused precious metals producer. I'd like to highlight some of the important achievements for the quarter. We produced approximately 96,000 gold equivalent ounces and remain firmly on track to achieve our 2026 production guidance for the 12th consecutive year.

David Rae
David Rae
President and CEO at DPM Metals

Vareš achieved commercial production in August, ahead of schedule, and remains on track to reach full production by year-end. We continue to deliver strong margins with an all-in sustaining cost of $1,580 per gold equivalent ounce sold, compared to an average realized gold price of $4,314. Navin will walk you through the drivers of our costs, including the impact of our strong share price performance, as well as other reconfirmed 2026 guidance. We generated $179 million of free cash flow, driven by strong operating performance and metal prices. We continue to return capital to shareholders, returning $81 million or 45% of free cash flow through our share buybacks and dividend payments, and we ended the quarter with $839 million of cash and $1.2 billion of total liquidity. Let me now turn to our operations and growth projects in more detail, starting with Vareš.

David Rae
David Rae
President and CEO at DPM Metals

We're very pleased with our progress at Vareš. In August, we achieved commercial production ahead of schedule, having exceeded an average of 60% of design throughput capacity and recoveries over 30 consecutive days. Vareš produced approximately 44,000 gold equivalent ounces during the third quarter, with an all-in sustaining cost of $767 per gold equivalent ounce sold. As a reminder, this reflects the capitalization of certain pre-commercial production costs, and we expect it to increase through the balance of the year while remaining within our guidance. Navin will have some additional color on this all-in sustaining cost at Vareš and our guidance expectations. We are on track to achieve the ramp-up to the 850,000 tons per year run rate by year-end, and we expect Vareš to exceed the high end of its production guidance range for 2026.

David Rae
David Rae
President and CEO at DPM Metals

I also want to address the recent decision of the Constitutional Court of Bosnia and Herzegovina, which was announced on October 1st. As you've heard from my commentary, operations at Vareš have continued as normal. This decision does not terminate or suspend the Vareš concession agreement. The court has ordered a six-month review period for the relevant authorities, along with the involvement of the Attorney General, to review the challenged acts for compliance with the Law on the Temporary Prohibition of Disposal of State Property. During that period, we're engaging directly with the state, federation, and cantonal authorities to represent our interests and to support a state-level solution to the state property issue in the country. Vareš has a strong local impact, employing over 700 people from Bosnia and Herzegovina.

David Rae
David Rae
President and CEO at DPM Metals

Under our ownership, we've made significant investments in safety, training, and leadership development, and we are the top exporter in the Zenica-Doboj Canton. We will continue to engage constructively with the authorities and will update the market if there are material developments. In the meantime, our focus at Vareš is unchanged, delivering a safe and successful ramp-up to full production, and we remain committed to being a responsible long-term partner in Bosnia and Herzegovina. Turning now to Chelopech, our flagship operation delivered approximately 50,000 gold equivalent ounces in the third quarter, in line with the mine plan, with an all-in sustaining cost of $1,460 per gold equivalent ounce sold. Chelopech is on track to achieve its guidance for the year.

David Rae
David Rae
President and CEO at DPM Metals

We are very pleased with the progress at the Wedge Zone prospect, which we will now refer to as Block 250, as it is incorporated into the Chelopech mine plan as a near-term opportunity. Block 250 is expected to grow production and extend mine life at Chelopech, with first production towards the end of 2028. We remain on track to complete an initial mineral resource estimate by year-end, and we are busy working to separate the operating activities and the preparation for the twin declines, including ventilation, such that the actual declines will commence being driven at the end of the first quarter of next year. We will also continue to explore the broader Wedge Zone corridor this year, including analogous structural settings along the Petrovden Fault.

David Rae
David Rae
President and CEO at DPM Metals

Turning to Brevene Porphyry South, our fourth significant discovery since 2023, we announced new high-grade intercepts in late September that confirm the system extends onto the Chelopech mine concession. Extended intercepts include 717 m at 3.3 g per ton gold equivalent and over 1 km at 2.5 g per ton gold equivalent. These results demonstrate the potential for scale and continuity, with broad continuous intervals of high-grade copper-gold porphyry mineralization. Drilling has confirmed a large potassic alteration envelope exceeding 500 m by 500 m and more than 1,000 m vertically. The system remains open to the north, south, west, and at depth. As we anticipated, the exploration license period concluded at the end of September, and we have shifted drilling to the Chelopech mine concession.

David Rae
David Rae
President and CEO at DPM Metals

We currently have 12 drill rigs focused on assessing the resource potential of the discovery, with up to 15,000 m of additional drilling planned through to year-end, and it will be continued delineating additional resource through 2027. We are targeting an initial resource estimate in the second half of 2027, which will form the basis of a preliminary economic assessment planned for the first half of 2028. In parallel, we continue to advance the conversion of the Brevene exploration license to a mining concession under the well-defined Bulgarian permitting process. In late August, we submitted the final geology report, which includes a technical and economic assessment, to the Ministry of Energy, and the regulatory review is ongoing. The key milestones from here include recognition of a commercial discovery, submission of a mining concession application, environmental and other permitting, and ultimately the granting of a concession contract.

David Rae
David Rae
President and CEO at DPM Metals

As we move through this process, our near-term exploration updates for the Chelopech camp will focus on results from within the mine concession, with further Brevene results to resume once the regulatory milestones are achieved. Block 250 and Brevene Porphyry South are two great examples of how we have transformed our growth outlook, creating an exceptional fully funded project pipeline that sets DPM apart from other mid-tier producers. Today, we have several attractive growth opportunities, including ÄŒoka Rakita. Following the October 25th parliamentary election in Serbia, administrative and regulatory decision-making timelines may be extended as the new government is formed and the National Assembly is convened. We will work with the relative authorities to align the scheduling of the next phase of the project if the process of the government's formation requires it, and we will provide timeline updates in due course.

David Rae
David Rae
President and CEO at DPM Metals

In parallel, we are continuing to advance engineering and procurement activities for the ÄŒoka Rakita project, including dismantling and refurbishing the Ada Tepe mill, ramping up purchases, and securing fabrication timelines for critical equipment. We are selecting the underground contractor and advancing detailed engineering. We remain committed to working proactively with all levels of government and local communities and to operating in accordance with industry best practices and applicable Serbian and European Union standards. Drilling at the Rakita camp continues to deliver encouraging results. Recent results from Dumitru Potok and Rakita North demonstrate that mineralization remains open along strike, laterally, and at depth. Drilling extended the marble-hosted intrusive skarn mineralization approximately 90 m west and 100 m southwest and returned encouraging results 300 m to the north of the existing mineral resource, indicating further expansion potential.

David Rae
David Rae
President and CEO at DPM Metals

These results improve our understanding of the mineralization geometry and indicate that mineralized tonnage may be greater than previously modeled. Given this success, we expanded our 2026 drilling program at ÄŒoka Rakita by an additional 12,000-15,000 m, focused on expanding the Dumitru Potok mineral resource, infill drilling, and target testing across the license. We expect to complete an updated Dumitru Potok mineral resource estimate by the end of the first quarter of 2027, and this will form the basis of a preliminary economic assessment targeted for completion by the end of 2027. With a significant gold-copper inferred mineral resource already defined at Dumitru Potok and the prospect open in several directions, we look forward to advancing the drilling program and continuing to define the potential of this organic growth prospect.

David Rae
David Rae
President and CEO at DPM Metals

As we reported in July, production at Ada Tepe concluded as scheduled on July the 15th, 2026, and mine closure activities are progressing well. As the first new mine in the Balkans in over 40 years, Ada Tepe has been a testament to DPM's ability to permit, build, and operate a world-class asset and implement standards that go above and beyond what is required. I particularly want to acknowledge the community for welcoming us, partnering with us, and working with us to create a world-class example of how mining can be conducted responsibly, with standards that go above and beyond those required and for the benefit of all stakeholders. We are now demonstrating responsible mine closure with 95% of the mine area expected to be returned back to Natura 2000, the European Union's nature protection network.

David Rae
David Rae
President and CEO at DPM Metals

I am proud of what we have accomplished at Ada Tepe, and I am confident that we are leaving a positive legacy for future generations. Before handing the call over to Navin, I will summarize our priorities for the remainder of 2026. We will be delivering the ramp-up at Vareš to the 850,000 tons per year run rate by year-end, and we will be advancing Čoka Rakita engineering and procurement activities while working closely with the authorities as the new government is formed. Our goal is to daylight value from our discovery of two tier-one potential gold-copper deposits. We will continue to execute on these priorities with the same commitment to responsible, efficient mining, financial discipline, and value creation. I will now turn the call over to Navin for a review of our financial results.

Navin Dyal
Navin Dyal
CFO at DPM Metals

Thanks, Dave. I will be touching briefly on the financial highlights for the quarter, provide an update on how we are tracking the guidance for the year, and conclude with some commentary on our balance sheet and return of capital program. Overall, DPM delivered strong financial results in the third quarter and record revenue, earnings, and free cash flow in the first nine months of 2026, benefiting from higher metal prices and the addition of the Vareš mine to our portfolio. Looking at our earnings and cash flow, revenue of $312 million in the quarter was 17% higher than the prior year, due primarily to higher realized metal prices and higher gold equivalent ounces sold, referred to herein as GEO, at Vareš following the acquisition in September of 2025, partially offset by lower GEO sold at Ada Tepe as the mine concluded its operations in July.

Navin Dyal
Navin Dyal
CFO at DPM Metals

Adjusted net earnings in the quarter of $144 million, or $0.66 per share, was 12% higher than the prior year due primarily to higher realized metal prices, higher GEO sold at Vareš, and lower cost of sales, partially offset by higher income taxes, higher exploration expenses, and higher mark-to-market adjustments to share-based compensation expenses. Adjusted net earnings included $17 million in depreciation expense related to the Vareš mine properties. The depreciable value of these mine properties reflected their carrying value together with the fair value adjustment recognized as part of the purchase price allocation upon the acquisition of Adriatic. Depreciation commenced on August 10th, 2026, when commercial production was declared.

Navin Dyal
Navin Dyal
CFO at DPM Metals

At full production rates over the life of the Vareš mine, annualized depreciation of these mine properties, net of the reversal of deferred tax liabilities associated with the fair value adjustment, is expected to be approximately $180 per ton of ore processed at Vareš. Adjusting items for the first nine months, which were not indicative of the company's operating performance, primarily included a $33 million reversal of certain provisions at Vareš, a $12 million fair value loss on the copper stream liability, and a $10 million loss on the settlement of a previously recognized receivable related to the DPM tolling agreement.

Navin Dyal
Navin Dyal
CFO at DPM Metals

Cash flow provided from operating activities for the quarter of $191 million was $7 million higher than the prior year due primarily to higher earnings generated in the period, partially offset by the timing of payments to suppliers and the timing of deliveries and subsequent receipts of cash. Free cash flow of $179 million for the quarter reflected an increase of $32 million compared to the prior year, due primarily to higher adjusted net earnings generated in the quarter. Taking a look at our cost metrics in the first nine months of 2026, all-in sustaining costs of $14.72 per GEO sold compared to an average realized gold price of $45.34 per ounce, reflecting the high margin, low-cost nature of our operations.

Navin Dyal
Navin Dyal
CFO at DPM Metals

All-in sustaining cost per GEO sold was 3% higher than the prior year, due primarily to higher costs at Chelopech and Ada Tepe as a result of the higher labor costs, higher energy costs, and a stronger Euro relative to the U.S. dollar, partially offset by lower all-in sustaining cost per GEO sold at Vareš due to the capitalization of certain pre-commercial production operating costs. All-in sustaining cost per GEO sold at Vareš is expected to increase for the fourth quarter as the gross operating costs at Vareš are now included in its all-in sustaining cost post-declaration of commercial production. All-in sustaining cost per GEO sold at Vareš for the full year is expected to be at the low end of the 2026 guidance range due primarily to lower gross operating costs and higher GEO sold.

Navin Dyal
Navin Dyal
CFO at DPM Metals

All-in sustaining cost was also impacted by mark-to-market adjustments to share-based compensation expenses, which resulted in an increase of $154 per GEO sold compared to an increase of $159 per GEO sold in the prior year, reflecting DPM's strong share price performance. We are on track to meet our all-in sustaining cost guidance for the year, and we are closely monitoring the market dynamics outside of our control, which impact costs such as metal prices, foreign exchange rates, and energy prices, and their movements compared to guidance assumptions. In terms of our capital spending for the quarter, sustaining capital expenditures of $8 million for the quarter were lower than the prior year due primarily to no capital expenditure at Ada Tepe as the mine reached the end of its life in July 2026.

Navin Dyal
Navin Dyal
CFO at DPM Metals

Partially offset by higher capital expenditures at Chelopech, due primarily to increased resource drilling and development activities. Growth capital expenditures of $26 million were higher than the prior year, reflecting the capital expenditures at Vareš, including the capitalization of certain pre-commercial production operating costs, partially offset by lower capital costs related to the Čoka Rakita project, due primarily to the timing of expenditures. Last night, we provided an updated three-year outlook supporting our continued focus on funding our exploration success and high-quality organic growth pipeline, while maintaining our portfolio of high-margin operations, which has generated our exceptional track record of delivery. The three-year outlook remains unchanged except for the following updates to the company's guidance for 2026.

Navin Dyal
Navin Dyal
CFO at DPM Metals

Based on positive results to date, exploration expenses are now expected to be between $75 million and $80 million to support additional drilling at Chelopech associated with the Brevene Porphyry South license, with initial mineral resource estimates targeted for the second half of 2027, and the Wedge Zone, also referred to as Block 250, also at Chelopech, where ramp development is commencing in the fourth quarter 2026, as well as Serbian drilling programs. At Vareš, growth capital expenditures are now expected to decrease to $90 million-$100 million, reflecting the earlier-than-planned declaration of commercial production and the corresponding lower capitalized pre-commercial production costs, as well as growth cash costs.

Navin Dyal
Navin Dyal
CFO at DPM Metals

At Chelopech, growth capital expenditures are now expected to increase to $9 million-$10 million to support engineering and design work related to the development of twin declines to Block 250, as DPM continues to target first production in late 2028. The three-year outlook for ÄŒoka Rakita project remains unchanged. Following the October 25, 2026 parliamentary election in the Republic of Serbia, the company notes that administrative regulatory decision-making timelines may be extended while the new government is formed and the National Assembly is convened. DPM is continuing to advance engineering and procurement activities for the project and remains committed to the project, with timeline updates, if necessary, to be provided in due course. We continue to maintain a strong balance sheet and cash position, with a consolidated cash balance of $839 million, no debt, and a $400 million undrawn revolving credit facility at the end of the quarter.

Navin Dyal
Navin Dyal
CFO at DPM Metals

With our significant strength and robust free cash flow, we are well-positioned to fund our growth opportunities and exploration prospects, while continuing to deliver peer-leading returns to shareholders through our enhanced share buyback program. In the first nine months of 2026, we repurchased four million shares at a total cost of $150 million under the company's normal course issuer bid, or NCIB, and paid approximately $27 million in dividends. From October 1 to November 11, 2026, we repurchased additional approximately one million shares at a total cost of $49 million, bringing year-to-date repurchases to approximately five million shares for an aggregate cost of approximately $198 million. We continue to deploy our capital in a disciplined manner that balances our desire to reinvest in growing and optimizing our business with our commitment to returning capital to our shareholders.

Navin Dyal
Navin Dyal
CFO at DPM Metals

In closing, we continue to deliver strong performance from our mining operations and continue our track record of generating significant free cash flow. We remain in a strong cash position and are focused on growth. I will now turn the call back to Dave for his concluding remarks.

David Rae
David Rae
President and CEO at DPM Metals

Thanks, Navin. This is an exciting time for DPM. DPM today is a premier mining business with industry-leading margins, lower-risk development assets due to their scale and quality, and a disciplined capital allocation strategy. This delivered share price outperformance for several years. With $839 million of cash, no debt, and a strong free cash flow, we are fully funded to deliver on our growth pipeline while continuing to return capital to shareholders. We remain focused on executing our strategy to deliver above-average returns for our shareholders as a mid-tier precious metals company with a clear path forward to drive value. I'd now like to open the call for any questions.

Operator

Thank you. As a reminder, to ask a question, you will need to press star one one on your telephone. To remove yourself from the queue, you may press star one one again. Once again, that is star one one to ask a question. Please stand by while we compile the Q&A roster. As there appear to be no questions in queue, I would like to turn the conference back to Jennifer Cameron for closing remarks.

Jennifer Cameron
Jennifer Cameron
Director of Investor Relations at DPM Metals

Well, thanks everyone for joining us. In the unlikely event that you were not able to get your question in, please feel free to reach out. You guys know where to find us. We also look forward to engaging through the balance of the quarter and look forward to share details of our upcoming investor day on December 8th. Thanks for the attention, and we will look forward to connecting.

Operator

This concludes today's conference call. Thank you for participating. You may now disconnect.